The VicSmart application form – where to start?
To start doing your own planning permit application, the first 5 things to you should know about the VicSmart application form are:
- To qualify for the VicSmart process, your project needs to meet the VicSmart criteria.
- Applications must be complete and include the information required by the application form and checklists.
- Applications for planning permits are decided on by your local council.
- If your application is eligible and you provide the required information, you will get a decision in 10 days – not 60 with delays. Note: the 10 days decision starts again after missing information is supplied.
- As of August 2014, local councils expected 40%-70% of VicSmart applications to be incomplete, of poor quality and consequently not decided within 10 days of lodgement.